Directcom to Finish Eagle Mountain Fiber to the Home Upgrades in 2018
The multi-year fiber-to-the-home upgrade construction project in Eagle Mountain will be completed in 2018. Over the past 3 years, Directcom has installed new fiber to about 4600 homes in Eagle Mountain. This means that over 8000 homes in Eagle Mountain now have access to fiber-to-the-home service. Our fiber upgrade project will continue through the end of 2018, so that by the end of the year, essentially every home in Eagle Mountain will have access to fiber to the home service.
So, who is getting fiber in 2018?
Looking at the network map of Eagle Mountain, the remaining subdivisions left on copper are: Mt Airey, Lone Tree Copper, Mustang Copper (North Ranch), and Rock Creek copper (includes Willow Springs, Simpson Springs and Kennekuk). This represents a total of about 600 homes or apartments still served by copper that will be upgraded to new Fiber.
First up to join the Fiberhood in 2018 will be Mt Airey and Lone Tree this spring, followed by North Ranch and the Rock Creek area towards the end of this year. We will be holding separate fiber open houses for Mt Airey and Lone Tree residents in March 2018, a couple of weeks before construction begins. These will be informal events where the company will further outline the construction schedule and upgrade plan, and answer any questions one-on-one about how the construction will affect you, how residents can best prepare for fiber to the home, and how fiber will improve the quality of life for residents in Eagle Mountain. We will send out invitations to those subdivision residents with more details at the beginning of March.
The tentative construction schedule to upgrade the remaining 600 homes in Eagle Mountain from copper to fiber will be:
Subdivision |  Construction Start |  Construction End | Cutover Start | Project Completion |
Mt Airey | Apr-18 | Jul-18 | Jul-18 | Oct-18 |
Lone Tree | Apr-18 | Jul-18 | Jul-18 | Oct-18 |
North Ranch | Jun-18 | Oct-18 | Oct-18 | March-19 |
Willow Springs, Simpson Springs and Kennekuk | Jun-18 | Oct-18 | Oct-18 | March-19 |
While main construction will be completed in 2018, individual fiber cutovers will likely extend into early 2019 due to this particular project difficulty, especially in the North Ranch area, where lots are larger, and the loop distances from the street to the actual home are longer than usual. This will require more time to install fiber to each home.
These last few construction projects are part of the push by Directcom to convert every neighborhood in Eagle Mountain to fiber.
During 2017, Direct Communications upgraded another 1300 homes to fiber. Chuck McCown, Operations Manager for Direct Communications, explained that the 2018 projects will be similar to the other projects completed in recent years, in that the in ground construction work will mostly be done by utility contractors, in order to speed up the upgrade process.
However, the final splice to the home and cutover to fiber at the home will be completed by Directcom’s own techs, who will be installing Optical Network Terminals on the outside of customers homes. Another contractor, Phelps Electric will be out at the same time installing outdoor power supply on houses to power the fiber electronics on the side of the homes. Since fiber does not carry an electrical signal like copper, each fiber terminal needs a power supply to power the electronics which convert the digital laser light to an Ethernet signal inside the home.
Kip Wilson, General Manager for Direct Communications in Eagle Mountain explained that areas have been prioritized carefully over the years as upgrade projects for various reasons such as:
- Whether the subdivision has existing duct already in the ground, which makes the capital investment cost requirement for the upgrade lower per sub,
- The distance from the central office to the subdivision, which can make the area more difficult to serve satisfactorily with copper,
- Higher number of potential customers: “We look at population density, and where we can provide the greatest benefit to the most people with the limited funding that we have available to us each year.”
- The condition of existing copper laid by the original property developers. Much of the original copper is in dire need of an upgrade, and where the old copper is causing the most problems for both customers and the network techs, the company will often seek to upgrade those areas to fiber first.
Generally, yards and gardens will not be disturbed, except where existing telephone pedestals are located at the corner of property lots– these pedestals will be replaced with handholes, which will be buried and placed level to the ground, which the company hoped would be welcomed by homeowners, since having no visible equipment would enhance curb appeal of the neighborhood. Most yards do have existing conduit from the old copper pedestals to the home, so crews should be able to pull new fiber through to the side of the house without disturbing the yards or lawns.
1 Gigabit speeds will be available to customers with fiber to the home. The company is currently accepting pre-orders for fiber service only for residents of areas under fiber construction who are not yet customers. Current customers will need to call our office once the infrastructure has been completed to schedule a 3 hour cutover to fiber appointment
Network Map of Current Fiber availability in Eagle Mountain Utah
Click on the “view larger map” icon on the top right bar of the network map below, and enter your address in the search field in the google maps interface to see if fiber is already installed at your home or future home.
Yellow areas are Fiber-to-the-home. Blue areas are still copper to the home, and will be upgraded to fiber in the future. Red is under fiber construction.